I do this quite a bit but just wanted to check with you guys and see where we recon I stand if it goes wrong.
I quoted for boiler replacement without upgrade of gas supply to 22mm and quoted separately for upgrading pipe 'if required'.
When commissioning I dumped the digital gauge in favour of the u-gauge and found it was perfectly good on the existing 15mm 🤔
My query is: if it failed (for arguments sake let's say 1.25mb drop) but the customer then refuses to pay to upgrade the pipe then where do I stand?
Surely I can't rightly commission and register the install should I AR it as not commissioned?
What stops them from then getting someone else to turn it back on and then register the install?
I guess I'd just need to make sure I kept the warning notice safe incase it came back at me?
I quoted for boiler replacement without upgrade of gas supply to 22mm and quoted separately for upgrading pipe 'if required'.
When commissioning I dumped the digital gauge in favour of the u-gauge and found it was perfectly good on the existing 15mm 🤔
My query is: if it failed (for arguments sake let's say 1.25mb drop) but the customer then refuses to pay to upgrade the pipe then where do I stand?
Surely I can't rightly commission and register the install should I AR it as not commissioned?
What stops them from then getting someone else to turn it back on and then register the install?
I guess I'd just need to make sure I kept the warning notice safe incase it came back at me?