hi, i've been passed a job locally that involves plumbing in a full system, running a heat-only sealed oil boiler.
i'm oftec, so oil side is no probs, but the customer wants to run property as two holiday lets with indipendent heating and shared unvented dhw.
i appreciate the dhw is simple enough, running independantly on its own tank stat.
i need advice on how to wire-plumb the two seperate living areas.
they are on ground level, the 5 rads in one half run off a manifold, as do the 5 in the other.
i am thinking i could fit a 2 port valve at each flow pipe as it reaches manifolds, to restrict flow to rads when they are satisfied by a pair of honeywell 921 prog rf roomstats.
is there a honeywell sundail plan i can look at that will perform this task?
ive fitted many 'y' plans, but this is a new project for me.
thanks.
i'm oftec, so oil side is no probs, but the customer wants to run property as two holiday lets with indipendent heating and shared unvented dhw.
i appreciate the dhw is simple enough, running independantly on its own tank stat.
i need advice on how to wire-plumb the two seperate living areas.
they are on ground level, the 5 rads in one half run off a manifold, as do the 5 in the other.
i am thinking i could fit a 2 port valve at each flow pipe as it reaches manifolds, to restrict flow to rads when they are satisfied by a pair of honeywell 921 prog rf roomstats.
is there a honeywell sundail plan i can look at that will perform this task?
ive fitted many 'y' plans, but this is a new project for me.