Hi there, I have a 50's ex council maisonette with cast iron stack. Customer wants toilet moved from ground floor to first floor. It's not possible to cut and tee into the stack and replace everything above the toilet in plastic as there is no access to the roof etc. I was thinking instead I'd cut the stack on 1st floor, put the tee in and then leave an air admittance valve there meaning I no longer need to connect into the open vent at roof level. That bit above the new loo could just be left redundant/sealed off. Anyone see any probs with this??
thanks in advance
thanks in advance