Hi folks,
I’m putting in a new bathroom above the kitchen and need to route the waste from the bathroom from above into a 4” in the kitchen. Is there a limit to the number of turns I should be making before the 1.5” feed into the boss?
I ask because there’re a load of copper pipes running along the wall and I need to bring it away from the wall a little to feed into the boss.
Not very well described but hopefully the photo helps! The waste will feed in from the right.
Cheers