Been asked to convert existing gravity HW to fully pumped system. | Plumbing Jobs | The Job-board | Plumbers Forums
  • Welcome to PlumbersTalk.net

    Welcome to Plumbers' Talk | The new domain for UKPF / Plumbers Forums. Login with your existing details they should all work fine. Please checkout the PT Updates Forum

Welcome to the forum. Although you can post in any forum, the USA forum is here in case of local regs or laws

American Visitor?

Hey friend, we're detecting that you're an American visitor and want to thank you for coming to PlumbersTalk.net - Here is a link to the American Plumbing Forum. Though if you post in any other forum from your computer / phone it'll be marked with a little american flag so that other users can help from your neck of the woods. We hope this helps. And thanks once again.

Discuss Been asked to convert existing gravity HW to fully pumped system. in the Plumbing Jobs | The Job-board area at Plumbers Forums

Status
Not open for further replies.

cr0ft

Plumbers Arms member
Plumber
Gas Engineer
Messages
3,311
Hi all. Usual thing, existing floor standing gas boiler is pumped for CH and running into a 28mm cylinder coil for DHW.

I am planning on capping off the CH flow and return at the boiler and converting the system into a y-plan fully pumped system.

Question for all. I realise the pipework is in 28mm for decent circulation by gravity. Is there any reason why I can't fit a 22mm y-plan kit then just use a 22/28 reducer after the valve to connect on to the existing 28mm?

I can't see a problem with this but wanted to check with people who have more experience of doing this than I!
 
That's how I've done them with no problems, just make sure there's no non return valve on it.
 
Will be fine imho.

might want to put a balancing valve in though?
more experianced guys can confirm this?
 
Will be fine imho.

might want to put a balancing valve in though?
more experianced guys can confirm this?

Do you mean a gate valve on the cylinder return? If yes it's not a bad idea, it'll help the heating circulation while there's hot water demand.
 
Jesus man alive . What are you on? Old. 28mm left in? Give your self a shake. That's loot.

I would try and use 22mm and fit s plan . Defo fit gate valve to cylinder. You know any sparkies who could wire s plan?
 
qe5a2e6a.jpg
 
Jesus man alive . What are you on? Old. 28mm left in? Give your self a shake. That's loot.

I would try and use 22mm and fit s plan . Defo fit gate valve to cylinder. You know any sparkies who could wire s plan?

I agree but even though the customer is moving in to the place he is doing everything as cheap as possible. Instead of going fully pumped he is now on about fitting a c plan kit..

I have informed him that my labour is the same either way. I know which one I would be fitting.

and no, I don't know any sparky that can wire an s plan sadly :)
 
I agree but even though the customer is moving in to the place he is doing everything as cheap as possible. Instead of going fully pumped he is now on about fitting a c plan kit..

I have informed him that my labour is the same either way. I know which one I would be fitting.

and no, I don't know any sparky that can wire an s plan sadly :)

Shouldn't be doing this really Croft, doesn't comply with part L.
 
Good point matey. I didn't think about that tbh. Why are honeywell still selling them then??
 
Good point matey. I didn't think about that tbh. Why are honeywell still selling them then??

for direct replacement only not for using to convert one to the other as then its a new installation and needs to comply
 
I don't know any sparky that can wire an s plan sadly :)

S Plan, Y Plan, W Plan, S plan Plus, C Plan, U Plan, c'mon none of them are rocket science, any decent sparx can do those
 
S Plan, Y Plan, W Plan, S plan Plus, C Plan, U Plan, c'mon none of them are rocket science, any decent sparx can do those

There's many a spark that baulks at the idea of wiring a heating system of any description. One of the lads I use wasn't keen until I spent some time going through how the water side worked, once he understood that then the wiring became easy for him.
 
S Plan, Y Plan, W Plan, S plan Plus, C Plan, U Plan, c'mon none of them are rocket science, any decent sparx can do those

Yay I got a bite. I am a spark and I am happy wiring them all in :)
 
That's an easy one. I'm not a gas safe engineer so I am a sparks first :) I don't do gas :)
 
I would say I am a plumber first before a spark as that's the trade I started in first!
 
I would say I am a plumber first before a spark as that's the trade I started in first!

What do you do for the gas then Kieran? I have a gsr engineer that will come in and do all the gas bits for me.
 
I go from one gsr to the next to be honest. Most I find seem to have a real bee in their bonnet about subcontracting to a non-gsr plumber!

To be honest I keep busy enough doing all the non-gas and electrical work. It would be nice to do the gas work but it's pretty much an closed off market under the current training requirements. But don't get me going on that again, it annoys me so much lol.
 
Status
Not open for further replies.

Similar plumbing topics

Everything working fine on PP mode - thanks...
Replies
7
Views
914
    • Like
That's either the VCP method or the combined...
Replies
19
Views
3K
And the greater the circulating height, the...
Replies
6
Views
2K
I just spoke to Potterton / BAXI support and...
Replies
1
Views
1K
    • Like
Alpha 2/3 manual. Shows variant with air...
Replies
8
Views
1K
Back
Top