E
easyt
I intend to raise a new shower base on 75mm celcon block and 15mm ply. I will duct for a replacement boiler feed pipe and fire control valve line. Also running the length of the shower (1700mm) I will provide a 22mm condensate pipe for future use. (Present boiler non-condensing). The regs say 3 degrees fall which I work out at 1 in 21.2 meaning 80mm fall over the length. I will struggle to achieve this. If I ran this section of pipe (say 2m long) at say 1 in 26 would this be likely to cause a problem. After the 2m run it is less than 1m to the drain and correct fall is available. In this situation what would you see as a minimum realistic fall.