wally5460
Hi can someone please offer me a bit of advice, my dad own a smallholding with farm buildings on it he is having mains water run to a location next to the main barn. bristol water have dug a trench to run the pipework and are coming to connect to the mains just inside the boundry of the land. I have been asked to run the pipework(approx 150m long in mdpe) and have it ready to connect to the meter when they come to install. My questions are........
1. what size connection will it be on the meter 1/2" or 3/4"?
2. do i need to put metal tags at 1m intervals along the pipe to aid future detection?
3. what type of connector is used to connect to the meter (screwfix page /item no. would be a great help)
4. are there any other special requirements ie dc vales etc.
I have good basic plumbing skills and knowledge but am usually fitting bathrooms and the radiator so a quick bit of guidance would be a great help.
Thanks
1. what size connection will it be on the meter 1/2" or 3/4"?
2. do i need to put metal tags at 1m intervals along the pipe to aid future detection?
3. what type of connector is used to connect to the meter (screwfix page /item no. would be a great help)
4. are there any other special requirements ie dc vales etc.
I have good basic plumbing skills and knowledge but am usually fitting bathrooms and the radiator so a quick bit of guidance would be a great help.
Thanks