Bernie,
I am reminiscing now
From what I remember of that almost forgotten art of lead work, I will start from seeing both lead sheet and pipe being cast and extruded in the lead mill
For sheet lead, there was a casting table about 6 foot by 8 feet and 6 inches deep with 4 removable L shaped lugs 2 on each long side, the joints were filled with fire clay, and the lead was cast into the table, when it had set, the lugs were removed and a crane was used to pick up the still hot sheet via U shaped lugs, the slab of lead was then placed onto a set of rollers in front of the mill (it looked like an overgrown "washing mangle") behind the mill there was another set of rollers, on either side of the set of rollers there was a circular saw blade, set in a sliding trough
The slab of lead was passed between the rollers, which were closed together until the required thickness was achieved, at times between the rolling the saw blade was run up and down the edges of the lead, to trim off the excess lead at the side of the roll, then when the sheet was the required thickness, the top end of the lead was trimmed by a person with a draw knife, and the first inch or so was placed in a slotted round bar, which was rotated to roll the lead sheet into a roll, whilst the lead was being rolled up the person with the knife was cutting the roll to the required length, 40 feet for a full roll, 20 feet for a half roll, this was then tied up with a hemp cord in 3 places
Sheet lead came in different thickness's by weight per square foot; 3lb, 4lb, 5lb, 6lb 7lb 8lb, anything over that was called plate lead, we nearly always used 5lb lead, on site, 7lb was about the best for bossing because it was thicker, but harder to work, whilst 3lb was too thin to work with and only fit for soakers
For lead pipe, the press was set in the ground and was about a foot across, the head of the "die" was clamped into place, the die had a roller which rotated with the lead passing the "die", also the "die" had a steel mandrel, the size of the pipe bore, held by 3 steel stays, from the outer edge of the "die", over the extruding press and just to on side there was a C shaped frame of rollers, at the far end there was a windlass
When the lead was cast into the press, and the "die head" had been clamped down, and the lead had set, the press was started the lead pipe came out of the press like tooth paste, the first couple of feet was cut off by a person with what looked like a table knife, because it was not a pipe but a solid rod of lead, then the person placed a cord over the lead pipe tieing it to the pipe with a clove hitch, the cord was lead over the C frame to the windlass, and two people started to wind the pipe into a coil of lead pipe
Lead pipe came different wall thickness and was sold by diameter / weight per foot, IE: 1/2 inch 5lb, or 1/2 inch 7lb; 3/4 inch 7lb, 3/4 inch 9lb
Which reminds me of a tale to tell, and that is even 50 years back, coppers were "bent", my mate was told to go to another job in the morning and was cycling home, with a coil of lead pipe on his shoulder, which was wanted for the job in the morning, when he was stopped by a "copper", who would not believe that the lead was wanted the next day, and "nicked" him it took the supervisor who drove to the station to get him released from the cell, but the police would not release the lead pipe, they said that he would have to go to the station in the morning to collect it, when he arrived at the station the next day, and asked for the lead pipe he was given about 6 inches of lead pipe, instead of the 10 feet the there was the night before, when he said that it had been nicked, he was given the station book to look at, the entry into the book was one piece of lead pipe!!, without the length of the pipe
Once the plumber was on site the first thing after being given a "shop" to work in, was the carpenter had to make up a bench for the plumber, made out of 8 x 2, at least 10 foot long (my mate once walked off the site because the general foreman was not going to allow the carpenter the time to make up the bench), then once installed with the pot lamp going if it was cold, work started, when the sheet lead arrived the performance started, (remember that a full roll of 5lb lead weighed the best part of 3/4 of a ton, 1600lbs), first a place was chosen for the sheet lead, then the floor was hard broomed, then sheets of plywood were laid down, for the lead to be unrolled on, this was then broomed off, then closely inspected for nails sharp stones etc, if the inspection of the plywood was OK, the lead was unrolled, the apprentice was then told to help set out the cut marks with the aid of a chalk line, but first take your shoes off if you are going to walk on the lead, I soon learnt after being hit with a dresser a few times
To cut the lead sheet a hook shaped "Draw knife" was used, first the tip of the knife was put in the mouth to give the end of the knife a bit of lubricant, and then working backwards on your knees the knife was drawn down the chalk line, and god help you if you so much as deviated from the chalk line by so much as a 1/16 of an inch, when the cut was deep enough, the cut piece was rolled up, again god help you if you rolled faster or slower than your mate because the lead would go off course and stretch on side so thinning that part of the lead
My old mate said to me once, I don't mind what time you get here, but when I arrive I want the shop to be warm, and my overalls to be warm for me to put on!, it was the same performance every morning, a few minutes before either 8 am summer time or 7.30 winter time, my old mate would turn up, put his overalls on roll a ***, then say "better go and have one then" of he would toddle to the bog coughing and spluttering, for half an hour, then say its not like the old days
The old days were from what I've been told, were from the first few years of the 1900's, when it was a 6 am start, breakfast was egg and bacon cooked on a clean shovel over a coke brazier, served at the bench covered with a clean painters dust sheet, the day was a 12 hour day, and the week was either a 6 day or a 51/2 day week, when I started it was a 51/2 day 56 hour week, for less than two quid a week, I can remember my father in about 1952 having a £5 note in his wage packet, and holding it up to the light saying I wonder if its genuine, this was the old "blanket" type note, white paper with black printing, his wage then was less than £10 a week
Plumbers today!!, you don't know your born, the job has gone soft, remind me to tell how the plumber was the "king" of the trades, and how he was respected when it came to sheet lead work or pipe work, and how the plumber treated the finished job with pride