Hi everyone,
Been asked to look at a job, the customer and his dad have already ripped out the cylinder and 90% of the old pipework and rads. They will be doing everything minus the gas pipework and fitting the boiler.
They have asked me to do it, they are decent guys to work for. They are not know it alls and will let me crack on.
It's their first home and they have gutted the place, they are obviously trying to save as much as they can. I'm happy to do the work, I have said I'd allow a day for it.
If there are issues with any of their work when it comes to filling and commissioning (might not be any) how would you price to sort out? I will be making them aware that sorting any issues with their work is not included in my price. I'm happy to help but it is the type of job that could be a fair days pay for the work done but should there be any problems I don't want to feel as though I have to sort it then discuss prices after.
Thanks
Been asked to look at a job, the customer and his dad have already ripped out the cylinder and 90% of the old pipework and rads. They will be doing everything minus the gas pipework and fitting the boiler.
They have asked me to do it, they are decent guys to work for. They are not know it alls and will let me crack on.
It's their first home and they have gutted the place, they are obviously trying to save as much as they can. I'm happy to do the work, I have said I'd allow a day for it.
If there are issues with any of their work when it comes to filling and commissioning (might not be any) how would you price to sort out? I will be making them aware that sorting any issues with their work is not included in my price. I'm happy to help but it is the type of job that could be a fair days pay for the work done but should there be any problems I don't want to feel as though I have to sort it then discuss prices after.
Thanks