Hi Guys
Went to look at a new build installation today for a builder i do a lot of work for, this is a Massive house and he hasnt had any drawing done he seems to think we can just wing it and hope it will be okay , may get away with that on a normal house but not on this ,
Am i correct in,
the maximum input must not exceed 70kw
iv volume must not exceed 0.035
meter can be u16 but must not exceed the iv
pipework no bigger than 35mm
the problem ive got is this house has got a swimming pool which is being done by a separate pool company and we do not have the specs
if for example we had 50kw input for boiler cooker etc then they come along and fit anything over 20kw we would be over the 70kw allowance
where would stand with doing our work staying in our tollerances and then them coming into do theres ? if it went over our scope then would we still be okay as they have installed after us ?? Ive asked the questions if we need to put any previsions in for them and the answer was a NO NOTHING TO DO WITH US,
surely it would make sense to know what they fitting to enable us to allow for the correct size pipework to the plant room , as we are fitting this , currently the gas meter is between 25 to 30 meters away and its a e6 ,
the impression i got is we only need to look after us , but im thinking is a e6 going to cope are we going to be out of our iv volume if he puts a big bum boiler in where does that leave us ????
I know its a bit sketchy as i dont have any drawing of them on the specs nor do i have the pool specs
Any comments appreciated
Thanks
Matt
Went to look at a new build installation today for a builder i do a lot of work for, this is a Massive house and he hasnt had any drawing done he seems to think we can just wing it and hope it will be okay , may get away with that on a normal house but not on this ,
Am i correct in,
the maximum input must not exceed 70kw
iv volume must not exceed 0.035
meter can be u16 but must not exceed the iv
pipework no bigger than 35mm
the problem ive got is this house has got a swimming pool which is being done by a separate pool company and we do not have the specs
if for example we had 50kw input for boiler cooker etc then they come along and fit anything over 20kw we would be over the 70kw allowance
where would stand with doing our work staying in our tollerances and then them coming into do theres ? if it went over our scope then would we still be okay as they have installed after us ?? Ive asked the questions if we need to put any previsions in for them and the answer was a NO NOTHING TO DO WITH US,
surely it would make sense to know what they fitting to enable us to allow for the correct size pipework to the plant room , as we are fitting this , currently the gas meter is between 25 to 30 meters away and its a e6 ,
the impression i got is we only need to look after us , but im thinking is a e6 going to cope are we going to be out of our iv volume if he puts a big bum boiler in where does that leave us ????
I know its a bit sketchy as i dont have any drawing of them on the specs nor do i have the pool specs
Any comments appreciated
Thanks
Matt