This is on my self build project.
6 loops of 120M each were laid on insulation in 100mm concrete screed.
The manifold was installed & pressure tested before the concrete was laid & held for a long time after.
That was over two years ago & the building has had no heating in all this time.
Just installed a new ground source heat pump & immediately found a split pipe at the manifold.
On repairing this pipe we have tried pressuring the system & found major leaks on 3 out of the 6 circuits, one so bad that no pressure at all reads with the filling loop fully on.
my options 1. resign myself to only running 3 loops... not good as the room with the canbus temp sensor won't be heated.
2. try leak sealer products .... doubt they'd be much good at the flow rate I'm loosing.
3. listen for the sounds of the leaks & dig them up ... not good spent a fortune on granite tiles.
Major delay on heating partially from ICE energy going bust & taking my deposit with them..
More than a bit depressing right now....
6 loops of 120M each were laid on insulation in 100mm concrete screed.
The manifold was installed & pressure tested before the concrete was laid & held for a long time after.
That was over two years ago & the building has had no heating in all this time.
Just installed a new ground source heat pump & immediately found a split pipe at the manifold.
On repairing this pipe we have tried pressuring the system & found major leaks on 3 out of the 6 circuits, one so bad that no pressure at all reads with the filling loop fully on.
my options 1. resign myself to only running 3 loops... not good as the room with the canbus temp sensor won't be heated.
2. try leak sealer products .... doubt they'd be much good at the flow rate I'm loosing.
3. listen for the sounds of the leaks & dig them up ... not good spent a fortune on granite tiles.
Major delay on heating partially from ICE energy going bust & taking my deposit with them..
More than a bit depressing right now....