G
Gus
I'm installing an 8kw wood burning stove with flue boiler, which should generate about 2.5kw to heat the DHW by gravity/thermosyphon. I'm also fitting a heat leak rad (old cast iron one rated at about 1.3kw).
I have a few queries though about the design and layout of the pipework. The HW cylinder is almost directly above the stove, so pipe runs are very short (not much more than 2m). I'm using 28mm pipe and can get a decent rise on the feed and fall on the return. The problem is the heat leak rad. In theory it should T off after the feed to the cylinder, but if the pipework has to rise to the rad, then it'll have to T off immediately after the T into the cylinder to have any rise at all. (it's positioned right next to the cylinder, but the inlet is only about 4" higher than the cylinder inlet) I was going to reduce the pipe from 28mm to 22mm after the cylinder, rising to the open vent, so the rad feed could also be 22mm. The question is:
1. Is this going to work efficiently (i.e. heating the DHW first and only heating the rad when it's hot) or will I end up heating the cylinder and rad together?! (I know I can't put a valve on the rad, as HETAS say it should be un-valved for H&S)
2. If I T off for the rad BEFORE the cylinder with 22mm pipe, would this make the situation even worse, or would the smaller bore pipe limit the flow of water to the rad giving reference to 28mm feed to the cylinder?
Hope this makes sense!!
I have a few queries though about the design and layout of the pipework. The HW cylinder is almost directly above the stove, so pipe runs are very short (not much more than 2m). I'm using 28mm pipe and can get a decent rise on the feed and fall on the return. The problem is the heat leak rad. In theory it should T off after the feed to the cylinder, but if the pipework has to rise to the rad, then it'll have to T off immediately after the T into the cylinder to have any rise at all. (it's positioned right next to the cylinder, but the inlet is only about 4" higher than the cylinder inlet) I was going to reduce the pipe from 28mm to 22mm after the cylinder, rising to the open vent, so the rad feed could also be 22mm. The question is:
1. Is this going to work efficiently (i.e. heating the DHW first and only heating the rad when it's hot) or will I end up heating the cylinder and rad together?! (I know I can't put a valve on the rad, as HETAS say it should be un-valved for H&S)
2. If I T off for the rad BEFORE the cylinder with 22mm pipe, would this make the situation even worse, or would the smaller bore pipe limit the flow of water to the rad giving reference to 28mm feed to the cylinder?
Hope this makes sense!!