Can anyone give handy advice for pricing repair jobs, please? Do I add a % on parts? What about a PRV that's hard to get to? Do you take the difficulty into consideration?

Appreciate any advice
 
Fair enough, I just want to be fair and up front. I think I overcharged for a job and don't want to overcharge again. I never charged an hourly rate. Just fixed prices. Curious how others worked it out
 
Fair enough, I just want to be fair and up front. I think I overcharged for a job and don't want to overcharge again. I never charged an hourly rate. Just fixed prices. Curious how others worked it out
If you know how long it will take then you can work an estimate out. The difficulty with repairs is that you don't usually know how long it will take as you often do not know the issue and by the time you have diagnosed it, you can be well into the time it will take to finish it.

Sometimes I have diagnosed a fault but need a part so I can estimate the cost of continuing. I would work it out at our rates x the time I think it might take, add 25% gross onto parts as a minimum and be clear that it is an estimate and will not cover other issues that could arise, particularly on older appliances.

Hope that helps.

If you are feeling guilty about over pricing something, don't. It could have gone the other way. That is the reason we don't tend to give prices for repairs, it is difficult without knowing what needs doing.
 
If you know how long it will take then you can work an estimate out. The difficulty with repairs is that you don't usually know how long it will take as you often do not know the issue and by the time you have diagnosed it, you can be well into the time it will take to finish it.

Sometimes I have diagnosed a fault but need a part so I can estimate the cost of continuing. I would work it out at our rates x the time I think it might take, add 25% gross onto parts as a minimum and be clear that it is an estimate and will not cover other issues that could arise, particularly on older appliances.

Hope that helps.

If you are feeling guilty about over pricing something, don't. It could have gone the other way. That is the reason we don't tend to give prices for repairs, it is difficult without knowing what needs doing.
Aye, I feel bad. Was even considering going back and giving him a few quid back 😂

I just estimated it incorrectly. I'll have to figure out a rock-solid way to estimate things.
 
repair work always hourly

What did you price wrong ?
 
I find it helpfull to think of the time I need to block off in the diary to be confident I'll get to the next job in time, as that's often longer.
Repairs are always an hourly rate tho so if I get it done an hour quicker, I reflect that in the price.
Customer will always appreciate £50 off more than a £50 cheaper quote and it shows integrity (even if its a bit engineerd).
 

Similar plumbing topics

Could be the expansion relief or an overflow...
Replies
1
Views
445
A
Hi all, I have a viessmann vitoden 100 w...
Replies
0
Views
641
Abbie S
A
Thanks for both replies - so the search is on...
Replies
2
Views
638
P
Tricky situation for you. Boiler shouldn't...
Replies
2
Views
561
  • Question
Hello Sergiu I would use it, but it's hard to...
Replies
1
Views
427