Got my merchant account through today ,with a covering letter of material price increases and there are some hefty increases
Rads due to steel prices and weakness of the £ are going up around 7%
Copper is priced on request but some cylinders have a 9% increase
All foreign shower products seem to be 5 to 8%
With quotes tight this could/will cut into job profits quite easily
It was mentioned the other day about conditions on quotes, maybe time to state quotation good for shot time frame
A heating job quoted last month, with go ahead next, is going to have a big increase in material costs,siduation is only going to get worse
So keep a tight eye on your materials costing for the for seeable future
Do not think and worry only about the big jobs ,if you are fitting a couple of rads and maybe new taps in the bathroom,you could see £20-£25 on materials, that may have to come out of your possible tight Labour charge
🙁🙁
even me fav Broag remeha is going up 2% at the end of the month
imho
Rads due to steel prices and weakness of the £ are going up around 7%
Copper is priced on request but some cylinders have a 9% increase
All foreign shower products seem to be 5 to 8%
With quotes tight this could/will cut into job profits quite easily
It was mentioned the other day about conditions on quotes, maybe time to state quotation good for shot time frame
A heating job quoted last month, with go ahead next, is going to have a big increase in material costs,siduation is only going to get worse
So keep a tight eye on your materials costing for the for seeable future
Do not think and worry only about the big jobs ,if you are fitting a couple of rads and maybe new taps in the bathroom,you could see £20-£25 on materials, that may have to come out of your possible tight Labour charge
🙁🙁
even me fav Broag remeha is going up 2% at the end of the month