Job was nearly 4 years ago and was a second fix only.
Hello Simon, hope you are well.
I don't know if you remember much about this job, but we are (finally) trying to get sign-off from Building Control. One issue they have raised is whether there is a soil vent pipe for the toilet. It seems like there isn't - do you recall if that is the case, and if so, was anything else done instead?
Thanks,
Job was nearly 4 years ago and was a second fix only.
Hello Simon, hope you are well.
I don't know if you remember much about this job, but we are (finally) trying to get sign-off from Building Control. One issue they have raised is whether there is a soil vent pipe for the toilet. It seems like there isn't - do you recall if that is the case, and if so, was anything else done instead?