Hi. I'm renovating a house and have replaced most piping.
The upstairs rads are fitted, but the downstairs is not as it's yet to be plastered. The pipes are just chased into the walls with Speedfit stop ends attached.
Can I go ahead and get the boiler replaced and the system working now and fit the downstairs rads later without many issues, or should I wait until the Joiners and plasterers have been and the whole system is installed?
Cheers,
David
The upstairs rads are fitted, but the downstairs is not as it's yet to be plastered. The pipes are just chased into the walls with Speedfit stop ends attached.
Can I go ahead and get the boiler replaced and the system working now and fit the downstairs rads later without many issues, or should I wait until the Joiners and plasterers have been and the whole system is installed?
Cheers,
David