Came across some houses where the carcass has been ran in screed. The pipe has been installed directly from outside into the floor and covered in screed, which makes the external pipe underground where it will be elbowed up into the meter box.
My concern is the sleeving. Sleeves should be sealed inside and outside left open. In this case it can't be left open if it's underground. At the moment there is just a pipe poking out a couple of bricks below the air bricks but once the houses are finished, where the pipe exists the property will be buried.
Any thoughts?
My concern is the sleeving. Sleeves should be sealed inside and outside left open. In this case it can't be left open if it's underground. At the moment there is just a pipe poking out a couple of bricks below the air bricks but once the houses are finished, where the pipe exists the property will be buried.