D
Dirty tree
Hi,
our plumbers installed a John Guest Wet single room 20m2 UFH into our kitchen extension.
Our floor space was 28m2 but they gave us a 20m2 system instead of a 30m2 system. They then installed only one single loop which is around 140m-150m long. Way over recommended length. Long and short is that only 1/3 of our room heats up.
They have admitted they ballsed up.John Guest have confirmed it has not been installed correctly.
We want all £1800 back. They are only offering £600 back.
To avoid us taking them to court they have come up with a "solution" to create two loops out of the one current single loop.
Here is their solution -
Remove all tiles necessary
· Channel 40mmW x 20mmD into the screed to a mid point on the loop.
· Cut into the loop, and connect two extra pipe to run back to the unit.
· Divide at the control unit as you would for the John Guest 30m2.
· House the connection point in a waterproof ply to strengthen the floor
· Re place the tiles.
The floor is 80mm concrete screed and 1200x1200 porcelain tiles with island and kitchen now all fitted and finished. They suggest to smash up the floor all paid for by their insurance.We have had enough of this and simply want our money back and be done with this.They say we are being obstructive for not allowing them to rectify the situation. We say they should have installed correctly the first time.
Our question to you the plumbing industry is this-
1.What are the issues involved in removing tiles, chasing into concrete, removing kitchen units,islands,skirting etc... can they hit or puncture existing pipe work?
2. Is this worth doing or best left alone as disruption and inconvenience will be immense.
( Our opinion is they want to do this because their excess on their insurance to cover these works is prob around £300 and our claim on them to refund all monies is £1800. You do the maths! )
3. What would you do as a customer in this situation?
Many thanks Guys.
our plumbers installed a John Guest Wet single room 20m2 UFH into our kitchen extension.
Our floor space was 28m2 but they gave us a 20m2 system instead of a 30m2 system. They then installed only one single loop which is around 140m-150m long. Way over recommended length. Long and short is that only 1/3 of our room heats up.
They have admitted they ballsed up.John Guest have confirmed it has not been installed correctly.
We want all £1800 back. They are only offering £600 back.
To avoid us taking them to court they have come up with a "solution" to create two loops out of the one current single loop.
Here is their solution -
Remove all tiles necessary
· Channel 40mmW x 20mmD into the screed to a mid point on the loop.
· Cut into the loop, and connect two extra pipe to run back to the unit.
· Divide at the control unit as you would for the John Guest 30m2.
· House the connection point in a waterproof ply to strengthen the floor
· Re place the tiles.
The floor is 80mm concrete screed and 1200x1200 porcelain tiles with island and kitchen now all fitted and finished. They suggest to smash up the floor all paid for by their insurance.We have had enough of this and simply want our money back and be done with this.They say we are being obstructive for not allowing them to rectify the situation. We say they should have installed correctly the first time.
Our question to you the plumbing industry is this-
1.What are the issues involved in removing tiles, chasing into concrete, removing kitchen units,islands,skirting etc... can they hit or puncture existing pipe work?
2. Is this worth doing or best left alone as disruption and inconvenience will be immense.
( Our opinion is they want to do this because their excess on their insurance to cover these works is prob around £300 and our claim on them to refund all monies is £1800. You do the maths! )
3. What would you do as a customer in this situation?
Many thanks Guys.