Hi all. I've just completed a new build and builders not happy with the invoice at all. What's new!
I could do with checking my price to make sure I'm not taking the p*ss as hes put it. Its doing my head in.
Its a detached four bed £500,000 house with bathroom and three ensuite shower rooms all done to a high spec. I let the builder supply all materials, so its labour only. I know its hard without seeing but what do you reckon?
Ive installed,
-Oil boiler
-Oil tank
-Ufh downstairs 6 zones
-10 rads and towel rails up
-300 litre unvented
-Bath
-Showers x3
-Basins x5
-Toilets x4
-Utility
-Kitchen
-Cloakroom/shower
-Outside taps x 2
No tiling.
Ive charged £5000 labour. No vat
Exact hours on site x £35
I know! I should have given a price for whole job and I'm going to from now on.
Cheers
I could do with checking my price to make sure I'm not taking the p*ss as hes put it. Its doing my head in.
Its a detached four bed £500,000 house with bathroom and three ensuite shower rooms all done to a high spec. I let the builder supply all materials, so its labour only. I know its hard without seeing but what do you reckon?
Ive installed,
-Oil boiler
-Oil tank
-Ufh downstairs 6 zones
-10 rads and towel rails up
-300 litre unvented
-Bath
-Showers x3
-Basins x5
-Toilets x4
-Utility
-Kitchen
-Cloakroom/shower
-Outside taps x 2
No tiling.
Ive charged £5000 labour. No vat
Exact hours on site x £35
I know! I should have given a price for whole job and I'm going to from now on.
Cheers