Hi all.
In need of some advice......
I have a customer who's boiler was classified unsafe. The existing system was a heat only boiler feeding a thermal store with no Y plan or S plan etc. My priory was to isolate the system, flush it and replace the boiler before Christmas. The issue I have now Is that I need to firstly get the pump overrun connected then get the controls updated. The customer declined a cylinder replacement.
I need an electrical minded engineer to advise me on the wiring as I'm struggling to get someone to help. The pump is connected with the room stat only at present and obviously removing the pump live would leave the room stat on its own. Is there any way around this as I don't want to leave it without overrun for too long whilst they make their mind up about the controls upgrade.
Thanks all!
In need of some advice......
I have a customer who's boiler was classified unsafe. The existing system was a heat only boiler feeding a thermal store with no Y plan or S plan etc. My priory was to isolate the system, flush it and replace the boiler before Christmas. The issue I have now Is that I need to firstly get the pump overrun connected then get the controls updated. The customer declined a cylinder replacement.
I need an electrical minded engineer to advise me on the wiring as I'm struggling to get someone to help. The pump is connected with the room stat only at present and obviously removing the pump live would leave the room stat on its own. Is there any way around this as I don't want to leave it without overrun for too long whilst they make their mind up about the controls upgrade.
Thanks all!