B
BurstPipe
Good afternoon all,
I have commenced an extension to my house and as part of this includes the main bathroom.
The proposed floor construction make up is 150mm type 1, DPM, 150mm concrete, 150mm Insulation, and 70mm Screed.
I plan to have all the subfloor pipework popups in-situ prior to pouring the concrete slab.
However, I have a few questions which I would be grateful for some advice:
1. What level should I run the sub floor pipework at? Within the type1 layer for the WC, sink, shower & bath? Surrounding the pipework in pea gravel.
2. Should I install 110mm underground pop ups to all fixtures & common them below ground to a main 110mm line? I had then just planned to install adaptors within the installation layer for the sink, bath & shower popups proposed to use 50mm for each.
The common 110mm would just go through foundations blockwork walls before discharging into a new external inspection chamber.
I plan to install a vent pipe upstream of this manhole to ensure the drain is ventilated.
Thanks in advance,
I have commenced an extension to my house and as part of this includes the main bathroom.
The proposed floor construction make up is 150mm type 1, DPM, 150mm concrete, 150mm Insulation, and 70mm Screed.
I plan to have all the subfloor pipework popups in-situ prior to pouring the concrete slab.
However, I have a few questions which I would be grateful for some advice:
1. What level should I run the sub floor pipework at? Within the type1 layer for the WC, sink, shower & bath? Surrounding the pipework in pea gravel.
2. Should I install 110mm underground pop ups to all fixtures & common them below ground to a main 110mm line? I had then just planned to install adaptors within the installation layer for the sink, bath & shower popups proposed to use 50mm for each.
The common 110mm would just go through foundations blockwork walls before discharging into a new external inspection chamber.
I plan to install a vent pipe upstream of this manhole to ensure the drain is ventilated.
Thanks in advance,