1) Seen in a public toilet in Dinan, I just could not believe it at first
2) Temporary electrical supply, the lead going off to the right crosses a public highway, and plugs into a meter box hanging off an electric pole, and the MCB in the meter box does not work
3) The distribution board (temporary), well he is an electrician !
4) The secondary vent off the W/C branch, green telephone gaine, (what is used to draw the telephone cable in from the water meter pit, to the central distribution point) an off-cut saves money, after all its his house
A point to note here is the purple chalk line snapped on the wall, this is the finished floor datum (who knows what this is ?, and better still uses one in the UK now ??) one metre up from FFL
5) Nothing wrong here, just showing the ends of the gaine's, green telephone, ready to go to pole just out of picture, the 100m red electric goes to a cut out box on the boundary, the grey 100mm pvc is rain water leading to the ditch
2) Temporary electrical supply, the lead going off to the right crosses a public highway, and plugs into a meter box hanging off an electric pole, and the MCB in the meter box does not work
3) The distribution board (temporary), well he is an electrician !
4) The secondary vent off the W/C branch, green telephone gaine, (what is used to draw the telephone cable in from the water meter pit, to the central distribution point) an off-cut saves money, after all its his house
A point to note here is the purple chalk line snapped on the wall, this is the finished floor datum (who knows what this is ?, and better still uses one in the UK now ??) one metre up from FFL
5) Nothing wrong here, just showing the ends of the gaine's, green telephone, ready to go to pole just out of picture, the 100m red electric goes to a cut out box on the boundary, the grey 100mm pvc is rain water leading to the ditch