Hi, I have a seaside apartment in Azerbaijan, currently a bare core & shell, not even internal walls yet, and am intending to put in wet UFH with ceramic tiles on top. Although we will get someone to do this for us, in my experience here it's always best to have a pretty good idea of what needs to be done first, to avoid any misunderstandings.
Apartment size is approx 80sqm and I've been told so far that:
I'd really like to validate those numbers to start with.
Thanks
Apartment size is approx 80sqm and I've been told so far that:
- there are 6m of pipe per sqm so 6x80 = 480m of pipe
- max 50m of pipe on each manifold, so approx 10 manifolds
I'd really like to validate those numbers to start with.
Thanks