C
caines
I'd appreciate your views/ thoughts/ advice on the following:
I had a new boiler fitted in 2008 and have the benchmark commissioning checklist completed and signed by the corgi registered plumber but corgi was never notified of the work so no commissioning certificate can be produced. The plumber was, but is no longer, Gas Safe registered and I can't get hold of him.
We were wrongly informed at the time that we did not need to have our work (garage conversion with new boiler) signed off by building control.
We are now trying to move and having a nightmare with building regs. I have been passed between building regs and gas safe so many time Im sick of speaking to them both.
The short of it is that the building control guy wants a boiler Commissioning Certificate before he can sign off the work from 2008. No other documents stating current safety status or even a recommissioning document will do (as its not a "certificate").
I understand from Gas Safe that a Commission Certificate can not be produced retrospectively.
So, is there any way of getting my "new" boiler signed off to comply with current building regs or do I just have to accept that as the Certificate can not be produced I can't get the building work signed off.
I'd appreciate your thoughts/ experiences.
Many thanks
Becky
I had a new boiler fitted in 2008 and have the benchmark commissioning checklist completed and signed by the corgi registered plumber but corgi was never notified of the work so no commissioning certificate can be produced. The plumber was, but is no longer, Gas Safe registered and I can't get hold of him.
We were wrongly informed at the time that we did not need to have our work (garage conversion with new boiler) signed off by building control.
We are now trying to move and having a nightmare with building regs. I have been passed between building regs and gas safe so many time Im sick of speaking to them both.
The short of it is that the building control guy wants a boiler Commissioning Certificate before he can sign off the work from 2008. No other documents stating current safety status or even a recommissioning document will do (as its not a "certificate").
I understand from Gas Safe that a Commission Certificate can not be produced retrospectively.
So, is there any way of getting my "new" boiler signed off to comply with current building regs or do I just have to accept that as the Certificate can not be produced I can't get the building work signed off.
I'd appreciate your thoughts/ experiences.
Many thanks
Becky