Hi all,
I did gas check and found gas meter istallation as follows.
Type:
Outside meter box
Surface mounted meter box
Pipe work: outlet pipe work go through brick wall not sleeved/sealed. the entry of the pipe work (outlet) within the meter box.
Inside the house, the pipe work goes under the concret floor.
Is this NCS or AR?
Please correct me
According to BS the outlet pipe work should come out the meter box then enter the property. (AR)
Also pipe work should be sleeved and sealed.(NCR)
Should I fail the test
Thanks
Sansks
I did gas check and found gas meter istallation as follows.
Type:
Outside meter box
Surface mounted meter box
Pipe work: outlet pipe work go through brick wall not sleeved/sealed. the entry of the pipe work (outlet) within the meter box.
Inside the house, the pipe work goes under the concret floor.
Is this NCS or AR?
Please correct me
According to BS the outlet pipe work should come out the meter box then enter the property. (AR)
Also pipe work should be sleeved and sealed.(NCR)
Should I fail the test
Thanks
Sansks