So what work are u planning to do? So far u just ripped out. Assume u had a GSR cap off the supply?
You should replace all the radiators
Run 15mm pipe from each rad to a central 22mm "spine" provide zones and trvs to suit output and a leak rad, including drain off at lowest points and avoiding air locks.
You should provide the installer with a 32mm solvent weld waste pipe connection at the proposed location,
You should clear a route for the gas supply - you cannot look at or touch it legally!
You can have a part p sparkie install a 13A fused spur within 1m of proposed location but sufficiently routed to avoid contravening regulations which apply to the gas pipe.
This will save you a few pennies but if it's a mess then could cost u a lot!
Also hot and cold will be required at the boiler location in 15mm copper.
You cannot use plastic within 1m of boiler on services.
You should replace all the radiators
Run 15mm pipe from each rad to a central 22mm "spine" provide zones and trvs to suit output and a leak rad, including drain off at lowest points and avoiding air locks.
You should provide the installer with a 32mm solvent weld waste pipe connection at the proposed location,
You should clear a route for the gas supply - you cannot look at or touch it legally!
You can have a part p sparkie install a 13A fused spur within 1m of proposed location but sufficiently routed to avoid contravening regulations which apply to the gas pipe.
This will save you a few pennies but if it's a mess then could cost u a lot!
Also hot and cold will be required at the boiler location in 15mm copper.
You cannot use plastic within 1m of boiler on services.