The original tender design was done by consultants in London and a spec produced for pricing. Wilmot Dixon won the contract on that spec. When the contract was signed, the consultants pulled the design and said WD had to use their own design to which they just rebadged the original with out checking to see if it will do the job, so the responsibility lies with them. Hence the QS sat with his head in his hands when we said it won't work. No one had told him why, the just refused to price the job.
So, if the job was tendered on a design, the design was pulled and they had to do it themselves (which presumably wasn't included in the original spec)..... let's see, redesign from the original, V.Os/AIs, I'm sure somebody looking at it on the contractual side could make a very good case for ££££££ of extras! :grin: